Brannan Andrus Levee Stability Berm

Delta Division Project in

Project Details

Client: Brannan Andrus Levee Maintenance District (BALMD)

View Photo Gallery

 

Project Description

Place Drain Rock at land side toe of levee as ballast to prevent slope slippage.

Major Challenges
Marina located at job site prevented direct placement by barge.

Project Scope
To off load 5,400 ton of Drain rock by barge into 10 wheel dump trucks, haul to job site 1 mile away and place as per lines and grades with dozer. Place stabilization fabric and to install water lines.